The test page is the tester's working paper: the procedure, the evidence notes, the attachments and finally the result and conclusion. Completing a test updates the control and can raise a deficiency.
Perform a test
- Open the test from Control tests or from the control's page.
- Select Start testing. The test moves to In progress.
- Under Working papers, change the Tester if needed and write the Test procedure and Evidence notes. Select Save (shown once you change something). You see "Working papers saved".
- Add the evidence (screenshots, exports, signed documents) under Attachments.
Record the result
- Select Record result.
- Fill in the fields below.
- Select Complete test. The test moves to Completed, for example "CT-2026-0010 completed: effective".
| Field | What to enter | Required |
|---|---|---|
| Result | Effective, Effective with exceptions or Ineffective. | Yes ("Choose a result") |
| Sample size | Items tested, as a whole number. | Yes |
| Exceptions | Items that failed, as a whole number. A test with exceptions cannot be Effective. | Yes |
| Conclusion | Your conclusion on the control. | Yes ("A conclusion is required") |
| Raise a deficiency when the control is not fully effective | On by default. | — |
When you complete a test:
- The control's Last result is updated and its next test falls due one frequency period later.
- If the result is not Effective and the checkbox is on, a deficiency is raised, owned by the control owner and due in 30 days:
| Result | Deficiency severity |
|---|---|
| Effective with exceptions | Deficiency |
| Ineffective | Significant |
| Ineffective, on a key control | Material weakness |
Cancel a test
Select Cancel test and confirm. The test is cancelled; the control keeps its due date.
Download the test
Select Download PDF for a printable copy of the test for audit files.
Statuses
| Status | Meaning | What you can do next |
|---|---|---|
| Planned | The test is planned and waiting. | Start testing, Record result, Cancel test |
| In progress | The tester is working on it. | Record result, Cancel test |
| Completed | The result is recorded. Attachments are read-only. | Download PDF |
| Cancelled | The test was cancelled. | — |
Differences by role
- Permission: