Portfolio
Also known as
- project portfolio
- PPM
- portfolio management
- roadmap
- health
- RAG status
- red amber green
- prioritisation
- prioritization
- project ranking
The portfolio ranks every project by its prioritisation score and shows its health from schedule and budget variance, with a roadmap by portfolio. Portfolio managers and leadership use it to decide where to put people and money.
Review the portfolio
- Open ProjectsPortfolio.
- Choose the Status values to include (draft, active and on hold by default) and a Portfolio, or All portfolios.
- Read the tiles: Projects, On track, At risk and Off track.
- In Prioritised projects, select a project to open it.
- Scroll to Roadmap to see the projects on a timeline by portfolio, coloured by health.
Columns
| Column | Meaning |
|---|---|
| Rank | Position by Score, highest first. |
| Health | On track, At risk or Off track (below). |
| % complete | Estimate-weighted progress of the WBS. |
| Schedule variance | Actual progress minus planned progress at today's date, in percentage points (pp). Negative is behind plan. |
| Budget consumed | Actual cost as % of budget cost. Red above 100 %. |
| Expected margin | Expected margin at completion; — for internal projects. |
| Priority | The manual priority, 1 (highest) to 5. |
| Score | 0 to 100: strategic fit, expected margin and inverse risk, weighted in settings, adjusted by the priority. |
How health is set
A project turns At risk when it slips behind plan, or runs over its earned value, by more than the Amber above threshold, and Off track above the Red above threshold or when it is over budget. Set the thresholds and the score weights in Projects settings. Set each project's Priority, Strategic fit, Risk and Portfolio on the project form.