Project revenue recognition
ProjectsRevenue recognitionPermission:
projects.revenue.runorprojects.report.viewOpen in Roari ERP (new tab)Also known as
- project revenue run
- POC
- percentage of completion
- percent complete
- completed contract
- WIP
- work in progress
- unbilled receivables
- revenue recognition
- rev rec
At month end, the revenue run recognises project revenue by percentage of completion or on completion, and posts the change since the last run to the ledger. Project accountants run it per legal entity; the history lists every run with its journal entry.
Run revenue recognition
- Open ProjectsRevenue recognition.
- Under New revenue run, Parameters: choose the Entity (empty = the default entity), set As of (usually the last day of the month) and, to run only some projects, choose them under Projects (empty = every billable project of the entity).
- Select Preview. The table shows, per project, the Method, Budget cost, Cost to date, POC, Recognisable, Recognised before, To post and WIP (unbilled).
- Check the figures and select Post revenue run, or Back to change the parameters.
The message Revenue run PRR-… posted confirms it. Select Open run to see it, or New run to start again. No project has revenue to recognise. means nothing changed since the last run. Running needs
Permission:projects.revenue.run.Posts when you select Post revenue run (one journal entry per run)
| Account | Debit | Credit |
|---|---|---|
| Project WIP | ✓ | |
| Project revenue | ✓ |
A negative change (revenue recognised earlier is no longer earned) posts the reverse.
Set the Project WIP and Project revenue accounts in Account mapping. A missing mapping stops the run.
How the amount is worked out
| Method | Revenue recognised to date |
|---|---|
| Percentage of completion | min(1, cost to date ÷ budget cost) × contract value. T&M projects without a contract value use their billings. Completed and closed projects count as 100 %. |
| Completed contract | Nothing until the project is completed; then the larger of the contract value and the billings. |
To post = recognised to date − recognised before. WIP (unbilled) = recognised − billed: positive is revenue earned but not yet invoiced (an unbilled receivable); negative is billed in advance.
Runs
The Runs list shows each run's Run number, As of, Entity, projects, Revenue posted, status and notes. Select one to open it: Revenue run.