The template editor defines a reusable plan: a header, a list of tasks with their nesting, start offsets, durations, estimates and predecessors, and budget lines. Task dates are offsets in days from the project start.
Build a template
- Open ProjectsSettingsTemplates and select New template (or a template to edit).
- Under Template, enter the Name, choose the Type, Billing method and Revenue method, add a Description and leave Active on.
- Under Tasks, select Add task for each task and fill in the row.
- Under Budget, select Add budget line for each cost category and enter the Amount and Hours.
- Select Save template. The message Template … saved confirms it.
Task columns
Keys link tasks: a parent key nests a task; predecessors read KEY:FS:lag or KEY:SS, comma separated.
| Column | What to enter |
|---|---|
| Key | A short unique key, for example A1. |
| Parent | The key of the summary task, or empty for a top-level task. |
| Name | The task name. |
| Start day | Days after the project start (0 = the start day). |
| Days | Duration in days, at least one. |
| Estimate h | Planned hours. |
| Milestone | Yes for a milestone. |
| Billable | Yes if time on it is billable. |
| Predecessors | For example A1, A2:SS, B1:FS:2 (type defaults to FS, lag to 0 days). |
| Message | Fix |
|---|---|
| Name the template. | Enter the Name. |
| Required. | Fill in Key and Name. |
| Keys must be unique. | Give each task its own key. |
| Unknown task key. | The parent or a predecessor names a key that does not exist. |
| Whole days from the start. | Enter Start day as a whole number, 0 or more. |
| At least one day. | Enter Days of 1 or more. |
| "…": use FS or SS. / "…": the lag is whole days. | Fix the predecessor text. |