Distribution requirements planning (DRP) keeps each destination warehouse stocked from its source warehouse. A DRP run nets forecast and backorder demand against stock and incoming supply in weekly buckets and proposes planned transfers; you review them and convert them into inventory transfer orders. Supply planners use it, typically weekly.
Before your first run
Set up the warehouse network in DRP network: one lane per destination with its source warehouse and transfer lead time. Without lanes, Run DRP is disabled (No lanes yet. Set up the warehouse network first.). Safety stock and reorder quantity per item and warehouse come from Item settings; the forecast comes from Demand forecasts.
Run DRP
You need Permission: supply_chain.drp.run.
- Open Supply chainDRP and select Run DRP (or type
run DRPin Ctrl K). - On the Parameters step, set the Horizon (days), pick the Destination warehouses (empty = Every lane destination) and add Notes. Select Next.
- On the Review step, read the summary: open planned transfers of earlier runs for these destinations are replaced. Select Run DRP.
The message DRP run DRP-…: n planned transfers appears and the run opens.
| Field | What to enter | Required / default |
|---|---|---|
| Horizon (days) | How far ahead to plan. | Required; DRP horizon (days) from settings, 56 in the demo |
| Destination warehouses | Warehouses to replenish. | Default: every lane destination |
| Notes | Why you ran it, for example "Weekly DRP". | Optional |
How DRP calculates
For each destination and item, per week over the horizon:
- Demand = the larger of the forecast (spread over the days) and open sales order backorders by requested date.
- Supply = open purchase order lines by expected date, open work orders (when Manufacturing is on) and inbound transfers in transit.
- Projected available stock starts from today's available stock. When it falls below Safety stock, a planned transfer covers the shortfall, rounded up to the reorder quantity and at least the lane's Minimum quantity.
- Needed is the start of that week; Ship by is lead-time days earlier. When that is before today the transfer is flagged Late; when the source warehouse does not have enough available stock it is flagged Short at source.
Runs list
The list shows Number, Run date, Status, Trigger, Horizon (days), Items, Planned, Converted and By. Select a run to open it, or Open planned transfers for the planned transfers of all runs.