Costing settings give the default labour and overhead rates used where a work centre has none, and decide how overhead is absorbed into work orders and standard costs. Cost accountants own them.
Change the rates
- Open ManufacturingSettingsCosting.
- Set the values below and select Save.
| Setting | What to enter | Demo value |
|---|---|---|
| Default labour rate per hour | Used for hours booked on a work centre without its own labour rate. | 40.00 |
| Overhead absorption | Per hour of work or Percent of labour. | Per hour of work |
| Default overhead rate per hour | Per hour mode: used where the work centre's overhead rate is 0. | 15.00 |
| Overhead (% of labour) | Percent mode: overhead = this % of the labour cost. | 50 % |
The rates apply to hours booked from now on and to the next cost roll-up; posted work orders are not recalculated.
What the rates post (per hour booked)
| Account | Debit | Credit |
|---|---|---|
| WIP | ✓ | |
| Labour absorbed into production (5510) | ✓ | |
| WIP | ✓ | |
| Overhead absorbed into production (5520) | ✓ |
The accounts are mapped in Account mapping (roles labour absorption, overhead absorption and manufacturing variance, created when Manufacturing is first enabled).