On the routing page you list the operations that make an item, with their work centres and times, and mark the ones done by a subcontractor or checked by quality.
Create a routing
- Open ManufacturingRoutings and select New routing.
- Under Routing, enter a Code and Name. Optionally pick the Item it makes by default, a Standard lot size and a Description.
- Under Operations, select Add operation for each step and fill in the columns (below).
- Select Save. The message Routing … saved. appears.
- Select Activate to make it usable (save your changes first).
Fields
| Field | What to enter | Required / default |
|---|---|---|
| Code | Short code, letters, digits and - _ . /. | Required: "Enter a code". |
| Name | A descriptive name. | Required. |
| Item | The item this routing makes by default (optional; Any item otherwise). A BOM without a routing uses the item's active routing. | Optional. |
| Standard lot size | Setup time is spread over this quantity in the cost roll-up. | 1. |
| Description | Free text. | Optional. |
Operations (at least one: "Add at least one operation"):
| Column | What to enter |
|---|---|
| Seq | Sequence number (10, 20, 30…). Must be unique: "Sequence numbers must be unique". |
| Operation | The name of the step, for example "Cut panels". |
| Work centre | Where it is done ("Choose the work centre"). Not needed for subcontracted operations. |
| Setup (min) | Setup time per work order. |
| Run (min/unit) | Run time per unit produced. |
| Subcontract | The step is done by a vendor. |
| Vendor | The subcontractor ("Choose the subcontractor"). |
| Cost / unit | The subcontract price per unit, for costing. |
| Lead (days) | Days the items are away at the subcontractor. |
| Inspection | Request an in-process inspection from Quality when the operation is reported. |
| Instructions | Work instructions shown on the work order, the traveller and the terminal. |
Activate, version and retire
| Action | Effect |
|---|---|
| Activate | The routing is used by BOMs and new work orders. Message: Routing … is active. |
| New version | Copies the routing into a new draft version to change it. |
| Obsolete | Read-only; not used by new BOMs or work orders. Refused while an active BOM uses it. |
| Delete (drafts) | Removes an unused draft after you confirm with Delete routing. |
An obsolete routing shows This routing is obsolete and read-only. Create a new version to change it.
How the times are used
Planned hours on a work order = setup + run × quantity. The cost roll-up charges (setup ÷ standard lot size + run) per unit at the work centre's labour and overhead rates, and MRP derives the make lead time from the routing hours at 8 hours a day plus subcontract days.