Work centres
Also known as
- work center
- workcentre
- machine
- resource
- production line
- cell
- calendar
- shift
- holiday
- overtime
A work centre is a machine, line, cell or team where operations are done. It has a calendar (working days, hours, holidays and overtime), a capacity and the labour and overhead rates that cost the hours booked there.
Look at a work centre
- Open ManufacturingWork centres.
- Select a work centre in the list (search with Search work centres). Until you do, the page says Select a work centre to see its capacity and calendar.
- Read its Hours per day, Machines or people, Efficiency, Capacity per day, Labour rate per hour, Overhead rate per hour, Working days, Day starts at, Warehouse and Open operations.
- The Calendar shows each day's available hours and booked hours for the month; use the arrows to change month. Days booked over capacity and calendar exceptions are marked.
Create or edit a work centre
- Select New work centre, or Edit on a selected one (needs Permission:
manufacturing.work_centre.manage). - Fill in the fields below and select Save. The message Work centre … saved. appears.
| Field | What to enter | Required / default |
|---|---|---|
| Code / Name | Identification. | Required. |
| Warehouse | Where the centre consumes and delivers stock. | Optional. |
| Active | Inactive centres are not scheduled. | On. |
| Description | Free text. | Optional. |
| Hours per day | Working hours of one machine or person. | Required: "Between 0 and 24 hours". |
| Machines or people | Parallel units working at the same time. | 1 (1 to 999). |
| Efficiency | Percentage of the hours that is productive. | 100 % ("Above 0 and at most 200"). |
| Labour rate per hour | Labour cost booked into WIP for each hour reported. | 0 = the default rate in Costing. |
| Overhead rate per hour | Overhead absorbed per hour. | 0 = the default rate. |
| Day starts at | Start time for scheduling (HH:MM). | 08:00. |
| Working days | The weekdays the centre works. | "Choose at least one working day". |
| Calendar exceptions | Per date: Hours (0 = closed) and a reason. Use them for holidays, short days and overtime. | Optional. |
| Notes | Free text. | Optional. |
Capacity per day = hours per day × machines or people × efficiency.
Delete a work centre
Select Delete. Work centres used by routings or work orders cannot be deleted; turn Active off instead.