Review an MRP run
ManufacturingMRPMRP runPermission:
manufacturing.mrp.viewAlso known as
- planned order
- convert planned orders
- firm planned order
- MRP exceptions
- expedite
- reschedule out
- past due
- pegging
- net requirements
- make or buy
An MRP run shows what the planning engine proposes: planned make and buy orders, the exceptions it found in existing supply and the netting per item. From here you firm, convert or cancel planned orders.
The header shows when the run was made, the horizon, the warehouses and who ran it, with the counts Items, Planned, Open, Exceptions, the Forecast source and Notes.
Review planned orders
The Planned orders tab lists one row per proposed order:
| Column | Meaning |
|---|---|
| Make / buy | Make becomes a work order; Buy becomes a purchase requisition. |
| Item, Warehouse, Quantity | What, where and how much. |
| Start | When to start (make) or order (buy). Late means the start date has passed. |
| Due | When the quantity is needed. |
| Level | The BOM level (0 = finished goods). |
| Demand | The sales order or parent item that causes it. |
| Vendor, Unit cost | The preferred vendor and cost for buy orders. |
| Status | Open, Converted or Cancelled. |
| Converted to | The work order or requisition created from it. |
Firm a planned order
To change a planned order before converting it:
- Select Firm on the row.
- Change the Quantity, Start or Due date.
- Select Firm. The message Planned order firmed. appears.
Convert planned orders
- Tick the planned orders to convert (needs Permission:
manufacturing.mrp.convert). - Select Convert.
The message Converted …: … lists the documents created: make orders become Plannedwork orders; buy orders become one purchase requisition per warehouse.
⚑ Approval
When Submit requisitions created from MRP for approval is on (MRP and scheduling), the requisitions go straight into approval under the rules in Approval rules; approvers act in Approvals. Otherwise they stay in draft for a buyer to check and submit.
Cancel planned orders
- Tick the planned orders you do not want.
- Select Cancel, then confirm. They are dropped from this run; run MRP again to re-plan.
Act on exceptions
| Exception | Meaning | What to do |
|---|---|---|
| Late | A planned order should already have started. | Convert and expedite it, or move the demand. |
| Expedite | Existing supply (PO or work order) is due after it is needed. MRP pulled it in rather than planning more. | Ask the vendor or the shop floor to bring it forward. |
| Past due | Sales demand dated before today. | Agree a new date with the customer. |
| Reschedule out | Existing supply is not needed within the horizon. | Push it out or cancel it. |
See why an item is planned
- Open the Items tab. Each row shows On hand, Safety, Gross demand, Scheduled receipts, Planned, Ending balance and Lead (d) per item and warehouse.
- Select a row. Pegging of … lists each demand and supply by date (sales order, forecast, dependent demand, work order material, safety stock, purchase order, work order, planned order) with the running Balance. Negative balances are red.