Capacity
ManufacturingCapacityPermission:
manufacturing.schedule.viewormanufacturing.work_centre.viewOpen in Roari ERP (new tab)Also known as
- capacity load
- capacity planning
- CRP
- load chart
- overload
- bottleneck
- available hours
- loaded hours
- utilisation
- work centre load
The capacity page compares the hours each work centre has available with the hours of scheduled operations, per day or per week, so planners can spot bottlenecks and overloads before they happen.
Check the load
- Open ManufacturingCapacity.
- Choose the Bucket: Day or Week, and use the arrows to move the period.
- Read the Available vs loaded hours chart, then the Load by work centre table: Period, Available h, Loaded h, Load (%) and Overloaded or Within capacity.
Available hours come from the work centre calendar: hours per day × machines or people × efficiency on working days, with calendar exceptions (holidays, short days, overtime) applied. Loaded hours are the scheduled operations from the last scheduler run and any moves since.
Fix an overload
| Option | Where |
|---|---|
| Move operations to another day or work centre | Schedule |
| Add overtime or a shift for a date | Calendar exceptions in Work centres |
| Add machines or people, or change the hours per day | Work centres |
| Re-prioritise or move due dates | Work order |
The same capacity feeds the Capacity load, next 4 weeks chart on the overview and S&OP in Planning.