The production schedule places every open operation on its work centre within the capacity of the work centre calendar, by priority and due date. Planners run the scheduler, look at the Gantt chart and drag operations to fix problems.
Run the scheduler
- Open ManufacturingSchedule.
- Select Run scheduler (needs Permission:
manufacturing.schedule.manage).
The message Scheduled … operations of … work orders (… late). appears and the line above the chart reads Last run …: … operations, … work orders, … late, … unscheduled. The scheduler plans forward from today over the Scheduler horizon (days) in MRP and scheduling: each operation after the previous one, on its work centre's working days, in the capacity left by operations scheduled before it. Subcontracted operations take their lead days on the Subcontracting lane. Planned work orders are included.
Read the chart
- One lane per work centre, one bar per operation (
WO-… · <operation>). A red bar ends after its work order is due. - Use the arrows and Today to move the window, and 2 weeks or 4 weeks to change its width.
- Hover a bar to see the operation, item and times; select it to open the work order.
Move an operation
- Drag a bar to a new start (1-hour steps), or onto another lane to change the work centre.
- With the keyboard: focus a bar, use the arrow keys to move it by a day, press Enter to confirm or Esc to cancel.
The message WO-… operation … moved to …. appears. A moved operation keeps its remaining hours from the new start and ignores other load, so check Capacity for overloads afterwards.