These settings are the defaults of every MRP run and of the production scheduler: how far ahead to plan, what counts as demand, the fallback lead times and whether MRP runs every night.
Change the MRP defaults
- Open ManufacturingSettingsMRP and scheduling.
- Set the values below and select Save.
| Setting | Effect | Demo value |
|---|---|---|
| Horizon (days) | Default planning horizon of MRP runs (7 to 730). | 90 |
| Minimum make lead time (days) | The shortest lead time MRP uses for make items. | 2 |
| Default buy lead time (days) | Used when the item has no lead time in inventory. | 7 |
| Include open sales orders | Default of the run parameter. | On |
| Include forecasts | Default of the run parameter. | On |
| Keep safety stock | Default of the run parameter. | On |
| Run MRP every night | MRP runs automatically early every morning with these defaults. | Off |
| Submit requisitions created from MRP for approval | Converted buy orders become requisitions that go straight to approval. | Off |
| Scheduler horizon (days) | How far ahead Run scheduler plans. | 60 |
⚑ Approval
With Submit requisitions created from MRP for approval on, requisitions from MRP follow the approval rules for requisitions as soon as they are created.
Related