Cost roll-up
ManufacturingCost roll-upsCost roll-upPermission:
manufacturing.cost.viewAlso known as
- apply standard cost
- standard cost update
- cost breakdown
- rolled-up cost
- cost change
- material labour overhead
- by-product credit
- costing run
- cost revaluation
- تحديث التكلفة المعيارية
A cost roll-up shows the rolled-up unit cost of each item, split into material, labour, overhead, subcontract and by-product credit, compared with the previous standard. From a draft you apply the result as the standard cost.
Review a roll-up
- Open ManufacturingCost roll-ups and select a roll-up.
- The header shows the date, the number of items, how many changed and who ran it, and any notes.
- Rolled-up unit costs lists each item per unit: Level, Item, BOM version, Material, Labour, Overhead, Subcontract, By-product credit, the total, the Previous standard and the Change.
- Select a line to open its Cost breakdown: every component and operation with its quantity, unit cost and amount.
Apply as the standard cost
- Open a Draft roll-up and select Apply as standard (needs Permission:
manufacturing.cost.rollup). - Read the confirmation: the catalogue standard cost of the items changes to the rolled-up totals. Confirm.
The banner Applied as the standard cost on …. appears and the status becomes Applied. From then on, new work orders snapshot the new standard, output is received at it and inventory uses it for standard-cost items.
Stock on hand is not revalued
Applying a roll-up changes the standard for new transactions only. Existing stock keeps its value; differences show up as production variances on work orders and as inventory's own variance for standard-cost items.
Related
- Cost roll-ups
- Bill of materials: the Cost tab shows each item's roll-up history
- Work order: standard against actual
- Items